Case Study Brief
The Installation Challenge
Restricted access through a 1 m × 1 m opening and 37 internal pillars complicated material handling, panel placement and sealing. The GeoDrain LD500, conductive Durafoil layer and 1.5 mm EVA membrane needed coordinated detailing within the reservoir.
Installation was sequenced around the access constraints and pillar interfaces. The drainage, conductive and containment layers were placed as the specified assembly, with welded EVA details and an electrical leak-detection survey supporting completion checks.
Installation Sequence
Prepare the reservoir
Review the supporting surfaces, access arrangements and pillar interfaces before introducing the lining materials.
Place the composite underlayers
Position GeoDrain LD500 and the conductive Durafoil layer in the specified assembly, maintaining continuity around the reservoir details.
Install and weld the EVA membrane
Deploy the 1.5 mm EVA panels and form seams, pillar collars and other interfaces to the project details.
Inspect, survey and hand over
Complete the applicable seam checks and electrical leak-detection survey, address identified defects and assemble the quality records.
Field Quality Assurance (QA/QC) Checklist
Quality checks recorded on this installation.
Products Used in Project
Products supplied and installed on this project.
“In-house project comment: This reservoir required one coordinated installation around 37 pillars. The drainage, conductive layer and EVA membrane each had a distinct role, and the detailing and inspection had to follow the complete assembly.