Geosynthetics Supply – FG Gold Process Ponds, Sierra Leone — 21,000 m²

Supply of geomembrane, protection geotextile and associated HDPE pipework for FG Gold process ponds in Sierra Leone, with coordinated material preparation and delivery.

ScopeSupply Only

Case Study Brief

FG Gold required geosynthetic materials and pipework for its process-pond works in Sierra Leone. Geosynthetics Africa coordinated the supply package and delivery arrangements. The scope included HDPE geomembrane, protection geotextile and solid HDPE pipework with custom flange details. Pipe diameters ranged from DN110 to DN315 to suit the project’s connections. Material identification and manufacturer documentation supported receipt checks against the order. The pipework was part of the process arrangement and should not be described as slotted drainage pipe. This case covers material supply. Site installation, seam QA/QC, pipe-joint testing and final commissioning remain separate from the supply documentation.

The Logistics Challenge

The Sierra Leone supply package combined geomembrane, protection geotextile and solid HDPE pipework with custom flange details. Material identification, packing and delivery coordination needed to cover a mixed package rather than liner rolls alone.

One coordinated geosynthetics and pipework package.

The supply scope brought together lining materials and DN110–DN315 pipe interfaces with consignment and delivery coordination. The pipework was solid custom-flanged HDPE, not slotted drainage pipe.

Logistics Route & Transit

How this consignment moved from order to site, stage by stage.

Route Timeline

1
Workflow 01Order preparation

Order and material schedule

Verify specified grades, dimensions and quantities against the project order.

2
Workflow 02Dispatch preparation

Consignment preparation

Coordinate material identification, packing, loading and the required shipment documents.

3
Workflow 03Transport coordination

Cross-border delivery coordination

Coordinate the required export, import and transport arrangements for the destination country.

4
Workflow 04Site receipt

Project-site receipt

Check the received material against the consignment and order; retain receipt and traceability records.

Products Supplied

Products supplied for this project.

“In-house project comment: The FG Gold package brought liner, protection geotextile and custom pipework into one coordinated supply scope. That connection helps keep the material interfaces visible from procurement through delivery.
IM
Ivan M
Project Manager · Geosynthetics Africa — internal project team

Submit your BOQ.

Get a quote – not just a price.

Upload your BOQ or speak to our technical team for expert recommendations and support.

Quick Contact

Global Best-in-Class Materials

Integrated into engineered systems

AmourRock logo
SoilLock logo
FlowTex logo
PolyTape logo