Supply OnlyMiningCross-BorderTanzania

HDPE Geomembrane Liner GRI-GM13 Supply, MCC Copper Mine Tanzania — 11,550 m²

Supply and cross-border delivery of 1.5 mm GSE® HDPE geomembrane for the MCC copper mine in Tanzania, with material documentation and coordinated road freight.

ScopeSupply Only
Logistics Tonnage11.5 ton
Distance Route3,400km
Borders Crossed4 borders

Case Study Brief

The MCC copper mine required 1.5 mm HDPE geomembrane for its containment works. Geosynthetics Africa supplied GSE® material specified to GRI-GM13 and coordinated delivery to the project in Tanzania. The supply scope covered material selection, order preparation and cross-border road freight. Roll identification and manufacturer documentation provided the basis for checking the consignment against the purchase requirements. Shipment planning brought together loading, customs documentation and delivery arrangements across the transit route. Preferential tariff treatment depends on the applicable origin rules and customs acceptance. This case covers supply and logistics. Installation quality, field seam testing and final acceptance form a separate project scope.

The Logistics Challenge

Transporting 11.5 tons of GRI-GM13-certified HDPE geomembrane from Johannesburg to the MCC Copper Mine site in Tanzania required a 3,400 km road route crossing three international borders. The consignment moved through Beitbridge , Kazungula and Tunduma border posts, each requiring full customs clearance, permit verification, and inspection. Rolled geomembrane is vulnerable to puncture and UV/moisture damage in transit, so load security and weatherproofing were critical throughout the multi-day haul. Coordinated pre-clearance documentation and real-time freight tracking ensured the shipment cleared both borders without delay, arriving on schedule for the client's installation

Cross-Border Compliance, Zero Damage

Every consignment was matched against certificates of origin, GRI test certification, and customs declarations before departure - with document detail cross-checked line-by-line to prevent border rejections. Rolls were secured with corner protection and weatherproof wrapping to guard against transit damage across 8 days on the road, resulting in on-spec, on-time delivery with zero material loss.

Logistics Route & Transit

How this consignment moved from order to site, stage by stage.

Route Timeline

1
Stage 01D0

Randburg Warehouse, South Africa

Ready stock dispatched ex-warehouse; export documentation and load security finalized.

2
Stage 02D0 - D+1

Beitbridge Border (South Africa → Zimbabwe)

Customs clearance, certificate of origin and GRI-GM13 test cert verification.

3
Stage 03D2 - D+3

Chirundu Border (Zimbabwe → Zambia)

Second customs checkpoint; documentation cross-check and load inspection.

4
Stage 04D4 - D+6

Tunduma Border (Zambia → Tanzania)

Final customs entry into Tanzania; permits and inspection cleared. Duration

5
Stage 05D7 - D+8

MCC Copper Mine Site Laydown

Final delivery and offload directly onto site laydown area, on schedule.

Logistics Document Chain

Documents prepared and tracked for this consignment.

01

AfCFTA Certificate of Origin

Issued

Confirms African-manufactured/originating status, enabling preferential customs duty treatment under the African Continental Free Trade Area across all border crossings on the route.

02

Commercial Invoice & Packing List

Issued

Itemized shipment value, roll count, and weight breakdown required for customs valuation and clearance at each border.

03

GRI-GM13 Test Certificate / Certificate of Conformity

Issued

Manufacturer's test report confirming the geomembrane meets GRI-GM13 property and thickness specifications.

04

Road Consignment Note / Cross-Border Transit Permit

Issued

Transit and carrier documentation authorizing road freight movement and customs bond coverage across each border post en route to Tanzania.

Products Supplied

Products supplied for this project.

Specification Conformity & Lab Verification

Key properties compared with the project specification.

PropertyTest MethodSpecification MinimumDelivered Value (Average)Margin Above Spec
ThicknessASTM D51991.50 mm nominal (-10% lowest individual)1.50 mmMeets Spec
DensityASTM D7920.940 g/cm³≥ 0.940 g/cm³Meets Spec
Tensile Strength at BreakASTM D669340 kN/m min avg40 kN/mMeets Spec
Puncture ResistanceASTM D4833480 N480 NMeets Spec
Carbon Black ContentASTM D42182.0–3.0%2.0–3.0%Meets Spec
“Highly recommended professional team.
FM
Flora Mramba
Procurement & Logistics Manager · MAST - MCC Copper Mine

Submit your BOQ.

Get a quote – not just a price.

Upload your BOQ or speak to our technical team for expert recommendations and support.

Quick Contact

Global Best-in-Class Materials

Integrated into engineered systems

AmourRock logo
SoilLock logo
FlowTex logo
PolyTape logo