Case Study Brief
The Installation Challenge
The existing reservoir had cracking and seepage, with vertical walls and inlet/outlet interfaces that required careful restraint and sealing. The 1,900 m² lining scope also had to support restoration of the community’s water supply.
The internal concrete surfaces were prepared before protection geotextile and reinforced PVC were installed. Hot-air welded panels, mechanical fixings and termination details formed the lining, followed by the reported successful first water test.
Installation Sequence
Prepare the existing concrete
Clean and prepare the internal surfaces and address cracks and rough areas before placing the lining assembly.
Install the protection layer
Position the 400 g/m² protection geotextile to cushion the reinforced PVC at the concrete interface.
Fit and weld the PVC lining
Cut and position the 720 g/m² reinforced PVC, complete hot-air welded seams and detail fixings, terminations and pipe interfaces.
Inspect and commission
Review seams and details, complete the water test and record the commissioning result and handover information.
Field Quality Assurance (QA/QC) Checklist
Quality checks recorded on this installation.
Products Used in Project
Products supplied and installed on this project.
“In-house project comment: This reservoir rehabilitation combined material suitability, wall restraint and detailed sealing around the existing interfaces. The recorded successful first fill supported restoration of the water supply.